Davis Elementary School
Davis is the clearest immediate rebuild recommendation. The current FCA places it in the highest condition-risk category of the five campuses.
Current and ongoing identified needs:
- Replacing most HVAC equipment
- Rebuilding or replacing the gym/activity gym
- Correcting water intrusion and drainage
- Replacing poor doors and non-ADA restrooms
- Addressing failing retaining walls, sidewalks, fencing, and playgrounds
- Reworking arrival and dismissal circulation
- Upgrading electrical panels, lighting, roofing, and interiors
That is no longer a limited repair program. It is a campus-wide renewal program. Rebuilding would give the district a safer, more efficient elementary school without preserving the complications of the original 1951 building, the 1978 gym, the 1989 annex, the 1993 addition, and the 2011 library.
2022 Assessment 2025 Assessment
Frequently Asked Questions
- What is the overall condition of Davis?
- How old is the building?
- How much work does the building need?
- What problems happen day to day, and how many work orders do they create?
- What were Davis’s utility costs in 2025–26?
- Why the proposed replacement of Davis instead of repairing it?